In April, the City Council awarded a $3.9 million contract to Universal Land Construction for the Tourist District Roundabout Project. This project includes the construction of three new traffic roundabouts along SR 202, in-lieu of traffic signals; storm drainage system upgrades; landscaping; decorative street lights, and sidewalks. The major portions of construction are scheduled to be complete by October 31, 2009 with remaining work to be completed in the spring of 2010. The project will be funded through City funds, a $2.1 million grant from the Transportation Improvement Board, and developer contributions.
What
is a Roundabout?
A roundabout is a circular intersection where traffic flows around a center island. Roundabouts eliminate the need for traffic signals and are safe and efficient way to move traffic along the road.
Safety: Engineering studies indicate that roundabouts reduce overall accidents by 40%, injury accidents by 75% and fatal accidents by 90%. Roundabouts are also designed for slower vehicle speeds, and there are no traffic signals to run through.
Traffic: Roundabouts help improve traffic circulation through roadway intersections because traffic now yields to other traffic rather than stopping at a signal.
More roundabout information is found at the Washington
State Department of Transportation (WSDOT). |
Watch
a Video on how to drive through a Roundabout.
|
UPDATES:
November 19: Construction work for the week of November 23 consists of the following activities: place permanent pavement markings and paint the driving lanes; power line trenching for street lights on the east side of Woodinville-Redmond Road; adjust water valves, manholes and catch basins to grade; and irrigation work throughout the project.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for striping and pavement marking placement and power trenching for street lights. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday and Tuesday and from 8:00 am to 12:00 pm on Wednesday.
Please note activities are weather dependent and may change due to rain-in particular, striping and pavement marking is subject to change due to weather because placement requires a dry surface.
No work is scheduled for Thursday or Friday in observance of Thanksgiving.
If you have any comments, questions or concerns regarding the planned and approved work on this project, please contact Dan Beck, Project Manager, 425.489.2700 x2295.
November 12:Construction work for the week of November 16 consists of the following activities: Install permanent signage at the east and west roundabouts; place permanent pavement markings and paint the driving lanes; install curb for splitter islands at the central roundabout; install truck apron at the central roundabout; irrigation work throughout the project.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for splitter islands construction, striping and pavement marking placement. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday. Delays up to 20 minutes should be expected.
Please note activities are weather dependent and may change due to rain.
November 5: Construction work for the week of November 9 consists of the following activities: Install permanent signage at the east and west roundabouts; place permanent pavement markings and paint the driving lanes; form and install curb for splitter islands at the central roundabout; energize the street lights; irrigation work throughout the project; fill areas backside of sidewalk eastside of the Woodinville-Redmond Road.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for splitter islands construction, striping and pavement marking placement. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday. Delays up to 20 minutes should be expected.
Please note activities are weather dependent and may change due to rain.
October 29: Construction work for the week of November 1 consists of the following activities: complete project paving, place pavement markings and striping, install curb for splitter islands at the central roundabout, install conduit for power and irrigation on 148th Ave NE and at the Central and East Roundabouts, and landscaping at various project locations.
WEEKEND WORK: Paving is expected to occur this weekend from 8:00 am to 3:00 p.m. if weather allows. Motorists should expect some traffic delays as intermittent lane closures are needed for splitter islands curb placement, final paving, striping, and for the installation of conduit for power and irrigation.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for splitter islands, curb placement, for final paving, striping and for the installation of conduit for power and irrigation. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday. Delays up to 20 minutes should be expected.
Please note construction activities are weather dependent.
October 22: Construction work for the week of October 26 consists of the following activities: pave final lift on SR 202 and 148th Ave NE; place pavement markings and striping; install curb for splitter islands at the central roundabout; install conduit for power and irrigation at central roundabout; install service cabinet for illumination at NE corner of NE 144th St and Woodinville-Redmond Road. Please note construction activities are weather dependent.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for splitter islands, curb placement, for final paving, striping and for the installation of conduit for power and irrigation. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday. Delays up to 20 minutes should be expected.
NIGHT LANE CLOSURES: Lane closures will be needed to complete the final lift of asphalt. The lane closures will be in place at night from 7:00 p.m. to 5:00 a.m.
October 15:Construction work for the week of October 19 consists of the following activities: pre-level paving at various project locations; remove asphalt and install curb on splitter islands at the west roundabout; continue installation of conduit for power and irrigation on the east side of the Woodinville-Redmond Road; install light poles on Woodinville-Redmond Road, NE 145th Street, NE 144th Street, 148th Avenue NE.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for asphalt removal and curb placement on splitter islands, and for the installation of conduit for power and irrigation. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday. Delays up to 20 minutes should be expected.
October 8: Construction work for the week of October 12 consists of the following activities: install stamped concrete at the Central Roundabout; saw-cutting for splitter islands at the Central Roundabout and East Roundabout; continue installation of conduit for power and irrigation on the east side of the Woodinville-Redmond Road; relocate water meter at the Chevron station; plug abandoned storm pipes; pour street light pole bases on Woodinville-Redmond Road; install street light poles, pre-level paving in preparation for final lift of paving later this month; tentative installation of fence at the Ball Field wall. Landscaping will begin on the east side of Woodinville-Redmond Road .
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for placing stamped concrete at the Central Roundabout, moving the water meter at the Chevron Station, saw-cutting the splitter islands at the Central and East Roundabouts, for permanent patching, and for installation of conduit for power and irrigation. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday. Delays up to 20 minutes should be expected.
October 5, 2009:Construction work for the week of October 5 consists of the following activities: removal of the traffic signal at the SR202 intersection Monday morning; aligning the Central Roundabout with traffic barrels; install temporary lane striping & blackout the old temporary striping; install truck curb at the Central Roundabout; grinding pavement at the Central Roundabout (SR202/ NE145th Street /148th Avenue NE intersection); continue installation of conduit for power and irrigation on the west side of the main intersection and then install the same on the east side of the Woodinville-Redmond Road; and install street light poles in the west leg of the main intersection and along the Hollywood Vineyard frontage.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for signal removal at the Central Roundabout, for grinding and placing curb, and installation of the light poles along NE 145th Street , and south along the Hollywood Vineyard frontage. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday.
September 24, 2009:Construction work for the week of September 28 consists of the following activities: placing patterned concrete in the truck apron at the Woodinville–Redmond Road/NE 144th Street intersection (south roundabout); start work on the Central Roundabout; additional pre-level paving, possible grinding of existing pavement, continue installation of conduit for power and irrigation on the west side of the main intersection, and install street light poles in the west leg of the main intersection.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for paving, installation of the light poles along NE 145th Street , and the work beginning at the central roundabout. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday.
September 17, 2009: Construction work for the week of September 21st consists of the following activities: pre-level paving at the central roundabout and Woodinville-Redmond Road / Woodinville Village Road / NE144th Street intersection (east roundabout); curb grading & curb pour at various locations on the project; continued installation of conduit for power and irrigation on the west side of SR202; grading for sidewalk on the west side of SR202; grade, pour, and stamp concrete at the NE 145 th Street / Woodinville Village Road roundabout.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for paving, curb installation, east roundabout setup and electrical & irrigation conduit installation. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday.
September 10, 2009Construction work for the week of September 14th consists of the following activities: pre-level paving at the central roundabout (148th Avenue NE); pre-level paving at Woodinville-Redmond Road / Woodinville Village Road / NE144th Street intersection (east roundabout); cone the east roundabout with traffic barrels; install conduit for power and irrigation on the west side of Woodinville-Redmond Road.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for paving east roundabout set up and conduit installation. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday.
NIGHT WORK/LANE CLOSURES: Tentatively, no project night work is scheduled for the week, but utilities may be working at night.
September 8, 2009Construction work for the week of September 8th, consists of the following activities: installing curb and gutter on the north and east side on NE 145th St., 148th Ave NE, Woodinville-Redmond Road and NE 144th St. and completion of the permanent patching in the roadway.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for curb grading, paving and permanent patching. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Tuesday thru Friday.
NIGHT WORK/LANE CLOSURES: Tentatively, no project night work is scheduled for the week, but utilities may be working at night.
August 27, 2009:Construction work for the week of August 31 consists of the following activities: completion of retaining wall veneer at the Hollywood School House and wall cap at the Mazatlan/Quilt Shop, as well as curb grading, permanent patching at different project locations, and paving at NE 145th St .
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for curb grading, paving and permanent patching. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday.
NIGHT WORK/LANE CLOSURES: Tentatively, no project night work is scheduled for the week, but utilities may be working at night.
August 20, 2009: Construction work for the week of August 24 consists of the following activities: retaining wall brick veneer construction and backfill at the Hollywood School House and complete retaining wall veneer at the Mazatlan/Quilt Shop, water tap installation at NE 145 th street , as well as asphalt removal, curb grading and permanent patching at different project locations.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for asphalt and concrete removal and permanent patching. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday.
NIGHT WORK/LANE CLOSURES: Tentatively, no project night work is scheduled for the week, but utilities may be working at night.
August 13, 2009:Construction work for the week of August 17 consists of the following activities: retaining wall brick veneer construction and backfill at the Hollywood School House and Mazatlan/Quilt Shop, asphalt removal, curb grading and grade for paving at different project locations. The road lowering at NE 145 th St. / NE 146 th Pl. was re-scheduled for the week of August 17 th .
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary road lowering on NE 145 th St. / NE 146 th Pl. The roadway cut is scheduled for Wednesday, August 19 th and traffic delays of up to 20 minutes will occur. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday.
NIGHT WORK/LANE CLOSURES: Tentatively, no project night work is scheduled for the week, but utilities may be working at night.
August 6, 2009:Construction work for the week of August 10 consists of the following activities: retaining wall brick veneer construction and backfill at the Hollywood School House and Mazatlan/Quilt Shop, backfill and grade for curb at different project locations and re-profile the road at NE 145 th St. / NE 146 th Pl.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for wall backfill, and road re-profile on NE 145 th St. / NE 146 th Pl. The road re-profile is scheduled for Wednesday, August 12 th and traffic delays of up to 20 minutes will occur. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday.
NIGHT WORK/LANE CLOSURES: Tentatively, no project night work is scheduled for the week, but utilities will be working at night.
July 30, 2009: Construction work for the week of August 3 consists of the following activities: retaining wall construction at the Little League Ball Fields, Hollywood School House and Mazatlan/Quilt Shop, pavement removal, temporary channelization and placing curb and gutter on Woodinville Redmond Road (west side) at Brian Carter Cellar's and Hollywood Vineyards mall.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary for wall backfill, pavement removal, curb and gutter and temporary channelization. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Thursday; and from 6:00 am to 2:00 pm on Friday.
NIGHT WORK/LANE CLOSURES: No project night work is scheduled for the week, but utilities will be working at night.
July 24, 2009: Construction work for the week of July 27 consists of the following activities: storm line work on Woodinville-Redmond Road NE, irrigation and illumination sleeve installation at the intersection of NE 145 th St/148 th Ave NE, finishing retaining wall construction at the Little League Ball Fields, Hollywood School House and Mazatlan / Quilt Shop, filling and paving on NE 145 th St and placing curb and gutter on Woodinville Redmond Road (west side) from south of Brian Carter Cellar's to north of Hollywood Vineyards mall.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary wall excavation, wall backfill, paving, irrigation and illumination sleeves installation and storm water installation. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday, Tuesday, and Thursday; from 5:30 am to 3:00 pm on Wednesday; and 6:00 am to 2:00 pm on Friday.
NIGHT WORK/LANE CLOSURES: Night work will continue for the week of July 27, for storm and sewer work at the SR 202 intersection and south on Woodinville Redmond Rd NE. Intermittent lane closures will be in place from 8:00 p.m. to 5:00 a.m., Monday thru Thursday.
July 16, 2009 Construction work for the week of July 20 consists of the following activities: storm water work on Woodinville-Redmond Road NE (Corner of NE 145 th St/148 th Ave NE ) irrigation and illumination sleeve installation, and retaining wall construction at the Little League Ball Fields, Hollywood School House and Mazatlan / Quilt Shop.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary wall excavation, wall pour, wall backfill, irrigation and illumination sleeves installation and storm water work. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday.
NIGHT WORK/LANE CLOSURES: Night work will continue for the week of July 20, for storm and sewer work at the SR 202 intersection and south on Woodinville Redmond Rd NE. Intermittent lane closures will be in place from 8:00 p.m. to 5:00 a.m., Monday thru Thursday.
July 9, 2009: Construction work for the week of July 13 consists of the following activities: storm water work on Woodinville-Redmond Road NE and illumination sleeves, clearing at the west side of SR 202, retaining wall construction at the Little League Ball fields, Hollywood School House and at the Mazatlan / Quilt Shop.
DAY LANE CLOSURES: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary wall excavation, clearing, irrigation and illumination sleeves installation. Lane closures will be in place from 8:00 a.m. to 3:00 p.m. Monday thru Friday.
NIGHT WORK/LANE CLOSURES: Night work will continue for the week of July 13, for storm and sewer work at the SR 202 intersection and south toward Woodinville Redmond Rd NE. Intermittent lane closures will be in place from 8:00 p.m. to 5:00 a.m., Monday thru Thursday.
If you have any comments, questions or concerns regarding the planned and approved work on this project, please Dan Beck, Project Manager, 425.489.2700 x2295.
July 2 , 2009: Construction work for the week of July 6 consists of the following activities: storm water work on Woodinville-Redmond Road NE and the SR 202 intersection, irrigation and illumination sleeves, and permanent asphalt patching at NE 145 th St , retaining wall construction at the Little League Ball fields, Hollywood School House and at the Mazatlan / Quilt Shop.
TRAFFIC IMPACTS: Travelers through this area should expect impacts on traffic as intermittent lane closures are necessary asphalt patching, wall excavation, irrigation and illumination sleeves installation and storm water installation.
NIGHT WORK/LANE CLOSURES: Night work will continue for the week of July 6, for storm and sewer work at the SR 202 intersection and south toward Woodinville Redmond Rd NE. Intermittent lane closures will be in place thru the week of June 29from 8:00 p.m. to 5:00 a.m., Monday thru Thursday.
If you would like to receive a weekly project update by email, please contact City Hall at 425.489.2700 x2240 to be included on the distribution list.
| Anticipated Schedule: |
|
| Construction Bids Open |
March 25 |
| Utility Relocation Work |
March thru June |
| Contract Awarded by Council |
April 14 |
| Contract Executed * |
April 25 |
| Work Begins * |
May |
| Remove Traffic Signal |
September |
| Project Completion |
Late Spring/ Early Summer 2010 |
* Based on receiving responsible bids within budget
If you would like to receive a weekly project update by email, please contact City Hall at 425.489.2700 x2240 to be included on the distribution list.
Project Information:
View roundabout design:


The roundabout system includes one main roundabout with
two internal travel lanes. The two smaller roundabouts
have single lanes and are located on the south and west sides
of the main roundabout. The smaller roundabouts act as slowing
devices for traffic before entering the main traffic circle.
Other improvements associated with this project include:
- Curb, gutter, street lighting, pedestrian walkways, street landscaping, and bicycle lanes
- Trail connection to the Sammamish River trail
- Water quality improvements for storm runoff
Through the use of roundabouts, the project will improve vehicle
and non-motorized safety, increase traffic capacity, make business
access easier and safer, and reduce noise and pollution.
The roundabout will eliminate the need for and delay caused
by the traffic signals at this intersection. Additionally, the
installation of these roundabouts is expected to dramatically
reduce rush-hour delays. It is projected that this particular
roundabout project will reduce the average wait per vehicle
during peak hours from 80 seconds to 50 seconds.
For more information regarding roundabouts, please visit Washington
Department of Transportation.
City Contact: Tom
Hansen , Public Works Director, 425.489.2700, ext. 2291